Village of Choudrant
Building
Permit
Procedure
Residential
permit
- Obtain 911
address
- Fill out
building permit
application
Supply set of
plans
Provide list
of contractors
-
International
2000 Building, NEC Electrical, Louisiana State Plumbing, And
International 2000 Mechanical Codes are to
be followed.
- Application
will be
reviewed by inspection and building permit will be issued. Do not begin
construction until notified by building inspection department.
Notify the
village at
the following stages of construction:
Immediately
prior to concrete pour
At completion
of electrical and plumbing rough-in, prior to interior seal out
(drywall, paneling etc. Installation)
At
substantial completion of construction. Allow
sufficient time for corrections
prior to occupancy.
- Certificate
of occupancy
will be issued after final successful inspection.
Commercial
permits
- Obtain 911
address
- Obtain Fire
Marshall’s
approval of plan design and provide letter of approval or stamped
plans.
- Fill out
building permit
application
Supply set of
plans
For new
construction, provide site plan to include parking lot construction,
landscaping and signage.
Provide list
of contractors
-
International
2000 Building, NEC Electrical, Louisiana State Plumbing, And
International 2000 Mechanical
Codes are to
be followed.
- Application
will be
reviewed by inspection and building permit will be issued. Do not begin
construction until notified by building inspection department.
- Notify the
Village at
the following stages of construction:
Immediately
prior to concrete pour
At completion
of electrical and plumbing rough-in, prior to interior seal out
(drywall, paneling etc. Installation)
At
substantial completion of construction. Allow
sufficient time for corrections
prior to occupancy.
- Certificate
of occupancy
will be issued after final successful inspection.
|